September 5, 2017

Roofing is on, HVAC installed and electrical rough ins are done! Waiting on Windows and exterior doors.

August 28, 2017

Framing done, working on electrical, HVAC and plumbing rough ins. Roofing should start this week. We are about to get some rain from the tropical storm.

August 11, 2017

Working on 2nd floor!

August 4, 2017

More framing! Should start trusses next week!

July 29, 2017

Framing!

July 26, 2017

We poured the slab!!! At 6am they started pouring. We had a small rainstorm and they hung out to make sure all was good. They just finished and it should be good and dry by Friday and this weekend to start framing.

July 25, 2017

Slab prepped and ready for slab pour.

July 10, 2017

Plumbing underslab complete! We are prepping for slab and then will get an inspection. We hope to pour the slab this week pending weather. The next 3 days calls for rain so lets all do our rain dance.

June 27, 2017

Laying block today

June 24, 2017

Footers got poured but the rain has kept us from laying block and doing plumbing underslab. Hoping for some dry weather next week!

June 16, 2017

We are underway! Prepping to our footers so pray for no rain for a week!