August 20, 2017

Lot 55 almost 100% complete!

July 15, 2017

Love the color!

May 11, 2017

Lot 53 – siding up and started drywall, Lot 55 – house wrapped, working on rough ins

May 1, 2017

Lot 53 – almost ready for insulation, siding, lot 55 – framing

April 17, 2017

Lot 55 formed, getting ready for slab

April 17, 2017

Framing complete on lot 53!

April 1, 2017

Slab poured! Should start framing late next week.

March 22, 2017

Prep for slab!