June 27, 2017

Flooring down, finishing touches!

June 8, 2017

Cabinets installed, tile shower getting installed!

May 27, 2017

Trim finished, 1rst coat of paint, cabinets delivered and will be installed next week

May 11, 2017

Drywall is going up!

May 1, 2017

Siding up, drywall this week!

April 17, 2017

Windows installed. Siding is going up soon.

April 1, 2017

Framing!!! Almost done and then we will set up frame walk.

March 22, 2017

Slab complete. Should start framing soon.

March 16, 2017

Slab poured, framing next week!