May 19, 2017

It’s looking gorgeous! Can’t wait to see you guys.

April 30, 2017

Exterior paint should be happening any day now. Cabinets are in process as well. Floors and counters are next! #mysabalstory

April 13, 2017

Your drywall is in. Hardiplank is installed as well. Trim and paint are next! #mysabalstory

March 29, 2017

Insulation is in, oak treads are in and your windows are going in as we speak. Drywall is dropped off and should be going in soon. #mysabalstory

March 22, 2017

Your home is wrapped and they are getting ready to start adding your hardiplank siding. They are also getting ready to start drywall soon! #mysabalstory

March 8, 2017

Framing is coming along! We will be in touch to schedule your FaceTime frame walk soon. #mysabalstory