May 19, 2017
It’s looking gorgeous! Can’t wait to see you guys.




April 30, 2017
Exterior paint should be happening any day now. Cabinets are in process as well. Floors and counters are next! #mysabalstory





April 13, 2017
Your drywall is in. Hardiplank is installed as well. Trim and paint are next! #mysabalstory




March 29, 2017
Insulation is in, oak treads are in and your windows are going in as we speak. Drywall is dropped off and should be going in soon. #mysabalstory





March 22, 2017
Your home is wrapped and they are getting ready to start adding your hardiplank siding. They are also getting ready to start drywall soon! #mysabalstory

March 8, 2017
Framing is coming along! We will be in touch to schedule your FaceTime frame walk soon. #mysabalstory
