May 1, 2017

Paint looks amazing!

April 17, 2017

Making some progesss! Installing granite! Working on master shower!

March 22, 2017

Putting up stone columns!

March 16, 2017

Siding up and drywall almost done!

February 15, 2017

Windows and doors installed! Working on rough ins now and Tuvek.

January 23, 2017

Framing started!!

January 4, 2017

Working on inspections and then plumbing underslab next week!

December 22, 2016

Block up! Plumbing underslab is next. Pray for no rain!

December 18, 2016

Footers are poured! Block has been dropped so they should start working on that next week.